Lease-Up Inspection Checklist
HOM, Inc. and Threshold recommend that owners and operators conduct their own inspection of the unit prior to the HQS inspection to ensure the unit is ready. The following is an abbreviated checklist to assist. All design elements that are present must operate as designed. The Housing Specialist will work with the Inspections Department to schedule inspections, and an Inspector can call you 30 minutes before arrival, if requested.
For any questions or to reschedule, contact out Inspection Department at inspectiondepartment@hominc.com.
Ensure all utilities, including electricity, gas, and water are on in the unit prior to the inspection.
Kitchen
- Fridge – sanitized at 37 degrees Fahrenheit
- Freezer – sanitized at 0 degrees Fahrenheit
- Range – cleaned with functional stovetop, oven hood vent and grease filter (if applicable), oven grates, and all knobs
- Garbage disposal functions properly if present
- Outlets are functioning GFCI within 3 feet of water source
- Countertop space available for meal preparation
Bathroom
- Toilet functions properly
- Exhaust fan and/or openable window
- Shower and/or tub has:
- Plug and Secondary drain cap available
- A secure drain
- No leaks/drips
- No Rust Mildew
- No Chipping
- Outlets are functioning GFCI within 3 feet of water source
- Door that closes and locks
Front/Living Room
- Front door opens, closes, and secures. Door has proper weather stripping, door sweep, threshold, jamb, and deadbolt in good condition
- Functioning smoke detectors
- Carpet/vinyl that is not lifted or damaged creating a tripping hazard
- Light fixtures, switches, and outlets have defect-free covers
- Window required and must open if designed to open. Picture windows are acceptable
Bedroom
- Must have either one outlet w/permanent light fixture or two outlets
- Must have an openable window w/lock or skylight. Thumb locks are acceptable
- Windows must not be damaged/cracked
- Security bars have functional quick release
Exterior
- All exterior doors have egress lighting that is functional
- Debris and shrubbery or grass overgrowth
- Walkway has no tripping hazards
- Cracks or breaks in stem wall and foundation)
- No water leaks/damages
- Paint is not chipped/peeling
- Fences and/or gates are fully operational and intact
- Leaking/water damage
HVAC and Plumbing
- AC & Heat function properly
- Swamp Cooler: 86 F max before failing
- Central Air: 82 F max before failing
- Air filter installed and clean
- Water heater with properly installed discharge line (TPR Valve)
- All water sources (sinks, toilets, showers, etc.) are free from any leaks or drips
- Fuse box has on exposed connections and missing blanks